Project Description
The N. Cedar Street Rehabilitation Project will improve the existing pavement surface, drainage, curbs, sidewalks and frontage improvements between W. Sacramento Avenue and W. 4th Street.


Funding
The total cost of this project is $3,000,000 and is funded by the Regional Early Action Planning (REAP) grant and Measure H.
Schedule
Project Approval and Environmental Document Phase – January 2026
Complete Design – April 2026
Construction – July 2026
Complete Project – October 2026